References

The beginnings of our team go back in the past when people were already involved in same or similar projects and fields of working.

Our team of people has vast experiences in the branch building turnkey or partial solutions.

With this knowledge, we can provide the best services in the field of Engineering, Installation, and Maintenance.

Some of the projects, where our team was involved are:

 

Pharmaceutical Factory (2025)

Year of execution: 2025

Area: UPS

Equipment used:

  • 1 unit Vertiv Liebert MTP 100kVA/100kW UPS

Picture6

Short project description:

Our client is one of Hungary’s leading pharmaceutical companies, which recently made two major production investments. The growth of the business area entailed the development and modernization of the IT area and the IT physical infrastructure. We joined this process with the delivery of the state-of-the-art Vertiv Liebert MTP 100kVA/100kW uninterrupted equipment, which, with its excellent characteristics and performance, is a suitable answer to the critical power supply task. With its high efficiency and small space requirements, MTP offers an optimal solution while reducing energy costs. With its exceptional reliability, this UPS guarantees a continuous power supply to protect critical equipment, preventing costly downtime and data loss.

 

Premium car manufacturer (2025)

Year of execution: 2025

Area: UPS

Equipment used:

  • Vertiv ITA2 10kVA + external battery cabinets

cp-ups-emea-508x635-ita2-10kva-20kva-family-hero

Short project description:

We delivered a 10kVA 3-phase Vertiv Liebert ITA2 UPS with true online double conversion technology, uniform output power factor and an extremely compact rack-tower design to our customer. The UPS is a perfect power protection solution for the secure uninterrupted power supply of IT equipment operating in one part of the factory.

 

W-SCOPE HUNGARY PLANT (2024)

Year of execution: 2024

Area: Cooling

Equipment used:

  • Liebert® PDX PI041+Liebert® HPA HCR59 (18 pcs)

Short project description:

W-Scope was founded as a developing, manufacturing and sales company of lithium-ion secondary battery separators. W-Scope Hungary plant is the first factory of this multinational company in Europe. For this project our company was responsible for delivery and start-up of the cooling units. At the same time we took over the installation works for the particular project segment. Cooling units are responsible for cooling down the transformer stations, which is the core of power supply for the whole factory.

Total built-in net sensible cooling capacity of all units is 624,6 kW.

 

Vehicle manufacturing technology (2024)

Year of execution: 2024

Area: UPS

Equipment used:

  • Vertiv Liebert GXT5  (20pcs) + External battery bank (15pcs)

Short project description:

The UPS devices we delivered are part of the communication infrastructure of the operating area. The factory’s communication center ensures the connection between the technologies of the body shop, the paint shop, and the assembly hall. Our uninterruptible power supply equipment provides reliable and secure physical infrastructure, enabling harmony between people and technology within short distances. Digitalization already plays a major role in the plant’s design, 5G technology embodies efficiency, sustainability, and digitalization. The engine of development is digitization for efficient processes and green operations. Digitization, from virtualization to artificial intelligence, makes data more transparent and processes more automated than ever before with applications that can be deployed immediately in the factory – thereby making production more efficient.

 

Electronics manufacturing sector (2024)

Year of execution: 2024

Area: DC Power Systems

Equipment used:

  • Vertiv NetSure 7100 (1 unit)

508x635-dc-netsure-7100-semibulk-emea-f

Short project description:

Our customer is a global manufacturing company with subsidiaries on three continents, employing over 10000 staff members, including over 1500 highly-qualified engineers and managers, equipped with enterprise technology centers, research labs, and robotic research centers. They focus on the design, development, and production of electronic products for world-renowned brands, with a special focus on IoT products and industry 4.0 production methodologies in various sectors including automotive, renewable energy, and consumer electronics. We supplied NetSure7100 DC power supply device for their plant in Hungary, which they use for testing purposes during the production process.

 

Automobile manufacturer (2024)

Year of execution: 2024

Area: UPS

Equipment used:

  • Vertiv Liebert GXT5 + MicroPod

Short project description:

Our customer required UPS devices with the manufacturer’s external maintenance bypass, which we solved with Liebert 2U MicroPod External Maintenance Bypass, which organically fits to GXT5 UPS. We supplied UPS solutions based on repetitive orders, that fulfilled further expectations like: parallel or redundant operation capability, high output power factor 1.0, SNMP web and ModBus communication, remote EPO and remote OFF functionality. We are proud that one of the leading premium car manufacturer now became a returning customer of Prom-Tech!

 

Government sector (2023-2024)

Year of execution: 2023-2024

Area: UPS

Equipment used:

  • Vertiv Liebert GXT5

Short project description:

Our UPS devices delivered to the professional communications service provider supports the applied digital communication solutions. The equipment supplied is part of the physical infrastructure of the critical and standby mobile communication system. Our UPS devices contribute to the efficient, safe, and reliable operation of the mobile telecommunications system.

Aggregated UPS power is 100kVA/100kW

 

MOL (2023)

Year of execution: 2023

Area: Monitoring&Management, Serial console

Equipment used:

  • 5pcs Vertiv Avocent ACS 8000 serial consoles

Short project description:

We delivered secure, remote access ACS console servers to our client. In this way, IT colleagues and network operation staff can remotely and safely manage computer rooms, including remote control, device inspection, equipment diagnostics and troubleshooting. This latest version features a dual-core ARM processor architecture and expanded memory capabilities.

 

Data Center – banking sector (2023)

Year of execution: 2023

Area: rack PDU Power Distribution Unit

Equipment used:

  • 190+ units Vertiv Geist intelligent rack PDU strip

Short project description:

Our company delivered the PDU devices to the facility, which was the largest data center investment in recent years. Measuring and switching by outlet was an expectation towards the intelligent distribution strips (Power Distribution Unit) that can be placed in the IT racks. The data center has a gross floor area of 2600m2 and was built in accordance with Tier III Uptime Institute infrastructure requirements.

 

Telecommunication sector (2023)

Year of execution: 2023

Area: DC Power Systems

Equipment used:

  • Vertiv NetSure

NetSure subrack photo

Short project description:

We supplied several users with 48VDC direct current power supply equipment for substation telecommunication systems. There was a need for a device that takes up little space, is energy efficient, highly efficient, and provides a reliable uninterrupted power supply to telecommunication devices. In addition, easy installation, quick commissioning, and easy serviceability were other considerations. Our devices have their own control and intelligent network monitoring.

 

Exhibition hall Budapest (2023)

Year of execution: 2023

Area: Cooling

Equipment used:

  • 8 pcs Vertiv Liebert HPM S1DKA+HCR 24

Short project description:

We have provided DX ”constant” cooling system for the room. In the room Air-cooled, direct expansion version, fitted with a scroll compressor precision Liebert CRAC units.

The required range of temperature/humidity in the rooms was:

  • The internal temperature: + 23 ±0,3ºC
  • Relative humidity: 50% RH ± 2%

Total built-in net sensible cooling capacity is 104 kW.

 

Car manufacturer (2023)

Year of execution: 2023

Area: Data Center physical infrastructure

Equipment used:

  • Complete data center cable tray system

Short project description:

PROM-TECH Hungary Kft. supplied complete data center cable tray system for one of the world’s leading brand car manufacturers. It was expected that the trays would run in a circle on each row of cabinets above the closed aisle rack systems. We were also able to meet the demand that the optical and copper cables could be routed separately from each other on the support structure.

 

Telecommunication company, Budapest server room (2023)

Year of execution: 2023

Area: Cooling

Equipment used:

  • 2pcs Vertiv Liebert PCW PH095DC

Short project description:

The room is cooled with 2 chilled water Liebert CRAC units.

The required range of temperature/humidity in the rooms was:

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%
  • Inlet fluid temperature: 7ºC
  • Outlet fluid temperature: 12ºC

Total built-in net sensible cooling capacity is 200 kW.

 

Bridgestone Magyarország Kft. (2023)

Year of execution: 2023

Area: rack PDU Power Distribution Unit

Equipment used:

  • Vertiv Geist UU30200 and GS30200 intelligent rack PDU strip

gs30200_front gs30200_rear

Short project description:

We delivered special PDU devices with combined outlets. Thanks to the C13 / C19 combination outlet solution, these rack PDUs can provide versatile rack power. The 2-in-1 (2-in-1) connection line functions both as IEC C13/C19.

 

Chemical industry, Budapest Server room (2023)

Year of execution: 2023

Area: Cooling

Equipment used:

  • 1 pc Vertiv Liebert FB009

Short project description:

Air-cooled water chiller with integrated Free cooling system, hermetic scroll compressors in the redundant configuration on two R410A refrigeration circuits with a plate heat exchanger evaporator.
Total built-in net sensible cooling capacity is 90 kW.

 

Electric Utility company (2023)

Year of execution: 2023

Area: UPS

Equipment used:

  • Vertiv Liebert EXS 30kVA

Short project description:

We offered a UPS solution, where the IGBT rectifier is capable to supply the battery charger with DC voltage at rated power, even if the UPS input AC voltage is below the nominal voltage specified. A further reduction of input AC voltage (within specified limits) shall inhibit the battery charger, while at the same time avoiding the discharge of the battery.

 

World leading IT company (2023)

Year of execution: 2023

Area: Cooling

Equipment used:

  • 2 pcs Vertiv Liebert CRV CR 30

Short project description:

The room was cooled with 2 chilled water precision in-row system devices
The requested air temperature/humidity was in the following range:

  • The internal temperature: + 24 ± 0,5ºC
  • Relative humidity: 45% RH ± 5%
  • Inlet fluid temperature: 7ºC
  • Outlet fluid temperature: 12ºC

Total built-in net sensible cooling capacity is 60 kW.

 

Chemical industry, Central Laboratory (2022)

Year of execution: 2022

Area: Cooling

Equipment used: 1 pc Liebert HPM SOFKA+HCR 14

Short project description:

We have provided DX cooling system (Air-cooled, direct expansion version fitted with a scroll compressor) for the Central Laboratory room.

The required range of temperature/humidity in the room is:

  •  The internal temperature: + 23 ±0,3ºC
  •  Relative humidity: 50% RH ± 2%;

Total built-in net sensible cooling capacity is 6 kW

 

Szamhead Kft (2015-2022)

Year of execution: 2015-2022

Area: UPS

Equipment used: 6 pcs Liebert APM (150kW)

Short project description:

Delivery, installation and start-up of modular UPS devices Liebert APM (6 pcs) with 150kW of total power each and with batteries for 10-15 min autonomy. Our company is in charge of regular maintenance and readiness service of these devices.

Total installed power is 900kW or 0,90 MW.

 

World leading networking company (2022)

Year of execution: 2022

Area: Cooling

Type of units used in the project:

  • 1 pcs Liebert PDX 033+HCR 43

Short project description:

We have provided DX cooling system (Air-cooled, direct expansion version, fitted with a scroll compressor) for the server room.

The required range of  temperature/humidity in the room was:

  • The internal temperature: + 24 ± 0,5ºC
  • Relative humidity: 45% RH ± 5%;

The total built-in net sensible cooling capacity is 30 kW.

 

Public Administration Server Room (2022)

Year of execution: 2022

Area: rack PDU Power Distribution Unit

Equipment used:

  • 100+ units Vertiv Geist intelligent rack PDU strip

Short project description:

In the server room, special requirements for the intelligent distribution strips were the socket type and quantity per section field and per phase, wide input voltage range and the possibility to integrate into building management system.

 

METRO stores (2016-2022)

Year of execution: 2016-2022

Area: Cooling

Equipment used:

  • Server room: 8 pcs Liebert HPM S1GUA+HCR 24, 

Short project description:

We have provided DX cooling system for the server room.  We have installed 78pieces Liebert CRAC air-cooled,  DX units fitted with a scroll compressor.

The required range of  temperature/humidity in the rooms is:

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%

Total built-in net sensible cooling capacity is 144 kW.

 

Telecommunication company (2022)

Year of execution: 2022

Area: UPS

Equipment used:

  • 1 unit Liebert APM (90kW) modular UPS

Short project description:

With this APM UPS device, the APM modular UPS installed base under the maintenance and readiness service of Prom-Tech Hungary Kft. increased up to 3,3 MW.

 

Automotive electrical systems factory (2022)

Year of execution: 2022

Area: Cooling

Type of units used in the project:

  • 2 pcs Liebert HPSE+HPSC 06

Short project description:

We have provided a cooling system for two individual Switch rooms with DX split precision Liebert Cooling units.

The required range of  temperature/humidity in the rooms was:

  • The internal temperature: + 30 ± 1ºC
  • Relative humidity: 35% RH ± 5%

The total built-in net sensible cooling capacity is 20 kW.

 

Public Sector (2022)

Year of execution: 2022

Area: rack PDU Power Distribution Unit

Equipment used:

  • 160 units Vertiv Geist intelligent rack PDU strip

Short project description:

There was a need for a special, 0U format, intelligent distribution strip inside the racks for a new server room environment. We delivered compact, measurable PDUs with splash-proof connector to meet customer requirements.

 

Telecommunication company (2022)

Year of execution: 2022

Area: Cooling

Equipment used:

  • 1 pc VERTIV PDX PX 047DF+1xDYS035

Short project description:

We have provided DX cooling system (Air-cooled, direct expansion version, fitted with a scroll compressor) for the server room.

The required range of  temperature/humidity in the rooms was:

  • The internal temperature: + 24 ± 0,5ºC
  • Relative humidity: 50% RH ± 5%

The total built-in net sensible cooling capacity is 40 kW.

 

Electric Utility company (2022)

Year of execution: 2022

Area: UPS

Equipment used:

  • Vertiv Liebert GXT5

Short project description:

The customer wanted to protect the costly and sensitive IT equipment they have, considering utilizing a generator on-site when utility power fails for a longer period.
We managed to implement a UPS solution that is highly available and flexible enough and has a unity power factor and high energy efficiency.

 

Banking and insurance sector (2021)

Year of execution: 2021

Area: rack PDU Power Distribution Unit

Equipment used:

  • 150+ units Vertiv Geist intelligent rack PDU strip

Short project description:

A financial services institution was seeking a solution for IT rack power distribution with intelligent management in their data center. We provided a solution with PDU devices featuring outlet level switching & outlet level monitoring at the same time. Each of the types supplied belongs to the best in the class category of PDU technology.

 

Telecommunications Budapest (2021)

Year of execution: 2021

Area: Cooling

Type of units used in the project:

  • 1 pc Liebert PCW PH145DC

Short project description:

We have provided a cooling system for the server room in three phases with a total of 5 pieces of Liebert CRAC chilled water precision units.
The required range of temperature/humidity in the rooms was:

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%
  • Inlet fluid temperature: 7ºC
  • Outlet fluid temperature: 12ºC

The total built-in net sensible cooling capacity is 145 kW.

 

Electronics industry server room (2021)

Year of execution: 2021

Area: Cooling

Type of units used in the project:

  • 1 pc VERTIV PDX PX 074DA+2xHCR 43

Short project description:

We have provided and installed a DX cooling system for the Server room (air-cooled, direct expansion Liebert CRAC unit fitted with a scroll compressor).
The required range of temperature/humidity in the rooms was:

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%

The total built-in net sensible cooling capacity is 30 kW.

 

IT service industry server room (2021)

Year of execution: 2021

Area: Cooling

Type of units used in the project:

  • 1 pc Liebert PDX PX 33 DA+HCR 43

Short project description:

We have provided and installed a DX cooling system for the Server room (air-cooled, direct expansion Liebert CRAC unit fitted with a scroll compressor).
The required range of temperature/humidity in the room was:

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%

The total built-in net sensible cooling capacity is 30 kW.

 

Chemical industry laboratory (2021)

Year of execution: 2021

Area: Cooling

Equipment used:

Type of units used in the project:

  • 1 pc Liebert HPM S1EOA+HCR 17

Short project description:

We have provided and installed a DX cooling system for the Laboratory (air-cooled, direct expansion Liebert CRAC unit fitted with a scroll compressor).
The required range of temperature/humidity in the room was:

  • The internal temperature: + 20 ± 2,0ºC
  • Relative humidity: 65% RH ± 4%; 50% RH ± 4%

The total built-in net sensible cooling capacity is 14 kW.

 

Military base (2021)

Year of execution: 2021

Area: Cooling

Type of units used in the project:

  • 4 pcs Liebert HPSE+HPSC 10
  • 2 pcs Liebert HPSE+HPSC 140

Short project description:

We have provided a cooling system for two individual Switch rooms in two buildings with a total of 6 pieces DX split precision Liebert Cooling units.
The required range of temperature/humidity in the rooms was:

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%

The total built-in net sensible cooling capacity is 70 kW.

 

National energy supply (2020)

Year of execution: 2020

Area: Cooling

Type of units used in the project:

  • 8 pcs Liebert HPW WM15MD
  • 2 pcs Liebert HPW WM08MD

 Short project description:

We have provided a cooling system for three individual Switch rooms in two buildings with a total of 10 pieces DX compact precision Liebert HPW Outdoor Package Cooling units.
The required range of temperature/humidity in the rooms was:

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%

The total built-in net sensible cooling capacity is 136 kW.

 

Building industry testing laboratory (2020)

Year of execution: 2020

Area: Cooling

Type of units used in the project:

  • 2 pcs Liebert HPM S1DOA+HCR 17

Short project description:

We have provided and installed a DX cooling system for the Laboratory (air-cooled, direct expansion Liebert CRAC unit fitted with a scroll compressor).s.
The required range of temperature/humidity in the rooms was:

  • The internal temperature: + 20 ± 2,0ºC
  • Relative humidity: 65% RH ± 4%; 50% RH ± 4%

The total built-in net sensible cooling capacity is 20 kW.

 

Chemical industry central laboratory (2020)

Year of execution: 2020

Area: Cooling

Type of units used in the project:

  • 2 pcs Liebert HPM S0HOA+HCR 14

Short project description:

We have provided and installed a DX cooling system for the Laboratory (air-cooled, direct expansion Liebert CRAC unit fitted with a scroll compressor).
The required range of temperature/humidity in the rooms was:

  • The internal temperature: + 20 ± 2,0ºC
  • Relative humidity: 65% RH ± 4%; 50% RH ± 4%

The total built-in net sensible cooling capacity is 14 kW.

 

Textile industry testing laboratory (2020)

Year of execution: 2020

Area: Cooling

Type of units used in the project:

  • Server room: 2 pcs Liebert HPM S0HOA+HCR 14

Short project description:

We have provided and installed a DX cooling system for the Laboratory (air-cooled, direct expansion Liebert CRAC unit fitted with a scroll compressor).
The required range of temperature/humidity in the rooms was:

  • The internal temperature: + 20 ± 2,0ºC
  • Relative humidity: 65% RH ± 4%; 50% RH ± 4%

The total built-in net sensible cooling capacity is 14 kW.

 

Magyar Telekom Budapest (2019)

Year of execution: 2019

Area: Cooling

Equipment used:

  • 4pcs Liebert PCW PH095DC

Short project description:

We have provided a cooling system for a Data Center with a total of 4 pieces of chilled water precision Liebert CRAC units. Our task was also the removal of the old units.

The required range of  temperature/humidity in the rooms was:

  • The internal temperature: + 22 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%
  • Inlet fluid temperature: 7ºC
  • Outlet fluid temperature: 12ºC

The total built-in net sensible cooling capacity is 400 kW.

 

Public institution (2019)

Year of execution: 2019

Area: Cooling

Equipment used:

  • 1pcs Liebert PCW PH080DC
  • 1pcs Liebert HPM S29OC

Short project description:

We have provided a cooling system for the server room with a total of 2 pieces Liebert chilled water precision CRAC units.

The required range of  temperature/humidity in the rooms was:

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%
  • Inlet fluid temperature: 9ºC
  • Outlet fluid temperature: 14ºC

The total built-in net sensible cooling capacity is 130 kW.

 

DENINET (2019)

Year of execution: 2019

Area: Cooling

Equipment used:

  • 2pcs Liebert HPM S29UC

Short project description:

We have provided a chilled water precision cooling system for the server room.

The required range of  temperature/humidity in the rooms were:

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%
  • Inlet fluid temperature: 7ºC
  • Outlet fluid temperature: 12ºC

Total built-in net sensible cooling capacity is 60 kW.

 

Hotel Budapest (2019)

Year of execution: 2019

Area: Cooling

Equipment used:

  • 2 pcs Liebert HPM S1DOA+HCR 17

Short project description:

We have provided DX cooling system for the server room. We have installed 2 pieces of Liebert CRAC direct expansion units, fitted with a scroll compressor.

The required range of  temperature/humidity in the rooms were:

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%

Total built-in net sensible cooling capacity is 40 kW.

 

Vodafone Hungary (2018-2019)

Year of execution: 2018-2019

Area: UPS

Equipment used:

  • 1pcs Liebert APM (120kW)

Short project description:

Delivery, installation, and start-up of modular UPS device Liebert APM (120kW) together with the installation of batteries with back –up time up to 15min.

 

Office building in Budapest (2018-2019)

Year of execution: 2018-2019

Area: UPS

Equipment used:

  • 2pcs Liebert EXL (400kW)
  • 4pcs Liebert EXL (200kW)
  • 2pcs Liebert EXL (100kW)
  • 1pcs Liebert NXC (30kW)

Short project description:

Delivery, installation, and start-up of all UPS devices together with the installation of batteries with back –up time up to 30min.

Total installed power is more than 1,8 MW.

 

Graphisoft Park Budapest (2018) 

Year of execution: 2018

Area: Cooling

Equipment used: 3 pcs VERTIV Liebert CRV21RA+HCR 33

Short project description:

We have provided DX cooling system for the server room. We have installed Liebert In the Row CRAC air-cooled,  DX units fitted with a scroll compressor.

The required range of  temperature/humidity in the room is:

  • The internal temperature: + 37 ± 1,0ºC
  • Relative humidity: 24% RH ± 5%

Total built-in net sensible cooling capacity is 60 kW.

 

TEVA (2018)

Year of execution: 2018

Area: UPS

Equipment used: 1pcs Liebert NXC (60kW)

Short project description:

Delivery, installation and start-up of UPS device together with the installation of batteries with back –up time up to 10min.

Our company is also in charge of regular maintenance and readiness service on this location.

 

International investment bank (2017-2018)

Year of execution: 2017-2018

Area: UPS

Equipment used:

  • 2pcs Liebert APM (120kW)
  • 2pcs Liebert NXC (15kW)
  • 2pcs Chloride Cross Rack (160A)

Short project description:

Delivery, installation, and start-up of modular UPS devices Liebert APM (2pcs) with 120kW of total power each and with batteries for 15min autonomy.  We have connected both devices to the system over STS switches.

Delivery, installation, and start-up of UPS devices Liebert NXC (2pcs) with 15kW of total power each and with batteries for 15min autonomy.

We also made a setup of LIFE services on all of the devices. Some of them are connected to LIFE over simple analog lines, some of them are using IP.

Our company is also in charge of regular maintenance and readiness service of these devices for the period of the next 5 years.

Total installed power is 270kW.

 

Nidec Sole Motor Bercel (2018)

Year of execution: 2018

Area: Cooling

Equipment used:

  • 2 pcs VERTIV Liebert PDX PX 031UA+HCR 43
  • 1 pcs VERTIV Liebert HPM S0FA+HCR 14

Short project description:

We have provided DX cooling system for the server room and hall. We have installed Liebert CRAC air-cooled,  DX units fitted with a scroll compressor.

The required range of  temperature/humidity in the room is:

  • The internal temperature: + 21 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%

Total built-in net sensible cooling capacity is 56 kW.

 

TechMahindra (2016-2018)

Year of execution: 2016-2018

Area: UPS

Equipment used:

  • 1 pcs Liebert APM (30+30kW)
  • 3pcs Liebert APS (10kW (2pcs), 20kW)

Short project description:

Delivery, installation, and start-up of modular UPS devices Liebert APM (1pcs) with 30+30kW and Liebert APS (3pcs). All the devices have installed batteries with back-up time up to 60min.

Our company is also in charge of regular maintenance and readiness service of these devices.

 

MILL Park Budapest (2018)

Year of execution: 2018

Area: Cooling

Equipment used:  2 pcs VERTIV Liebert PDX PX 054DA+HBR 88

Short project description:

We have provided DX cooling system for the server room. We have installed Liebert CRAC air-cooled,  DX units fitted with a scroll compressor.

The required range of  temperature/humidity in the room is:

  • The internal temperature: + 26 ± 1,0ºC
  • Relative humidity: 40% RH ± 5%

Total built-in net sensible cooling capacity is 100 kW.

 

CTBTO server Budapest (2018)

Year of execution: 2018

Area: Cooling

Equipment used:

  • 1 pcs VERTIV Liebert PDX PX 031DD+HCR 51

Short project description:

We have provided DX cooling system for the server room. We have installed Liebert CRAC air-cooled,  DX unit fitted with a scroll compressor.

The required range of  temperature/humidity in the room is:

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%

Total built-in net sensible cooling capacity is 21 kW.

 

Courthouse Hódmezővásárhely (2017)

Year of execution: 2017

Area: Cooling

Equipment used:

  • 1 pcs Liebert HPM S0HUA+HCR 17

Short project description:

We have provided DX cooling system for the server room. We have installed Liebert CRAC air-cooled,  DX unit fitted with a scroll compressor.

The required range of  temperature/humidity in the room is::

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%

Total built-in net sensible cooling capacity is 10kW.

 

Football Stadium Székesfehérvár (2017)

Year of execution: 2017

Area: Cooling

Equipment used:

  • 2 pcs Liebert PDX PX 33 DA+HCR 43

Short project description:

We have provided DX cooling system for the server room. We have installed 3 pieces Liebert CRAC air-cooled,  DX units fitted with a scroll compressor.

The required range of  temperature/humidity in the room is::

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%

Total built-in net sensible cooling capacity is 60 kW.

 

HIPO Budapest (2017)

Year of execution: 2017

Area: Cooling

Equipment used:

  • 3 pcs Liebert HPM S1GDA+HCR 33

Short project description:

We have provided DX cooling system for server room.  We have installed 3 pieces Liebert CRAC air-cooled,  DX units fitted with a scroll compressor.

The required range of  temperature/humidity in the room is:

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%

Total built-in net sensible cooling capacity is 47 kW.

 

APOLLO Tyres Hungary Gyöngyös (2016-2017)

Year of execution: 2016-2017

Area: Cooling

Equipment used:

  • MRS building: 4 pcs Liebert HPW WM15MD
  • PRS building: 4 pcs Liebert HPW WM15MD

 Short project description:

We have provided a cooling system for two individual Switch rooms in two buildings with a total of 8 pieces DX compact precision Liebert HPW Outdoor Package Cooling units.

The required range of  temperature/humidity in the rooms was:

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%

Total built-in net sensible cooling capacity is 120 kW.

 

National Instruments (Debrecen) calibration rooms (2016)

Year of execution: 2016

Area: Cooling

Equipment used:

  • Liebert PDX PX021 + HCR 43 (4pcs)

Short project description:

Two calibration laboratories used for calibration of sensors, instruments were provided with cooling system in 2N redundancy.

The required range of  temperature/humidity in this calibration rooms are:

  • The internal temperature : + 23°C ± 1,0ºC
  • Relative humidity : 45% RH ± 5%

The required range must be provided in six different measurement points in the room at the same time.

 

International investment bank (Budapest, 2016)

Year of execution: 2016

Area: UPS

Equipment used:

  • 2pcs Liebert APM (120kW)

Short project description:

Delivery, installation and start-up of modular UPS devices Liebert APM (2pcs) with 120kW of total power each and with batteries for 15min authonomy. We also made a setup of LIFE services for both devices.

Our company is in charge for regular maintenance and readiness service of this devices for the period of next 5 years.

 

Hamburger Hungaria (Dunaújváros) power plant (2015)

Year of execution: 2015

Area: UPS

Equipment used:

  • Central building: 2pcs Liebert PCW PH025HC
  • Electrical building: 4pcs Liebert PCW PH025HC, 4pcs Liebert PCW PH080HC
  • Turbine hall: 1pc Liebert PCW PH100HC

Short project desription:

We have provided cooling system for six individual rooms in three buildings with a total of 11 pieces of chilled water precision Liebert CRAC units.

The required range of  temperature/humidity in the rooms were:

  • The internal temperature: + 24 ± 1,0ºC
  • Relative humidity: 50% RH ± 5%
  • Inlet fluid temperature: 10ºC
  • Outlet fluid temperature: 15ºC

Total built-in net sensible cooling capacity is 410 kW.

 

Company dealing with mutual funds

Construction of a Highly Secure Room with 35m2 net space with complete support infrastructure in the following configuration: Uninterruptible Power Supply System (UPS) 60kW, Air Conditioning (2x35kW), Electrical installations with Switching blocks, Server and Communication Racks, Fire Extinguishing System with NOVEC1230 gas, Intelligent PDU’s, Designing.

image_r

 

Electrical institute

Super computer data center for hydrodynamic calculation. Scope of supply was: 1 x NXa 160, 1 x NXa 40, 6 x Cool therm 30kW, 1 x HPM 80kW, 1 x 250kW Chiller

image2_r

 

Pharmaceutical company

Construction of a Highly Secure Room with 30m2 net space with complete support infrastructure in the following configuration: Uninterruptible Power Supply System (UPS) 60kW, Air Conditioning (2x35kW), Electrical installations with Switching blocks, Server and Communication Racks, Fire Extinguishing System with NOVEC1230 gas, Intelligent PDU’s, Central Surveillance System, Designing.

image3_r